Greenfield covered bridge may re-open by summer

greenfield-covered-bridge

Large Map
  • Latest News
2 Pittsfield firefighters injured
2 Pittsfield firefighters injured

Two Pittsfield firefighters were injured while trying to put …

Tsarnaev court hearing postponed again
Tsarnaev court hearing postponed again

A federal judge has rescheduled a probable cause hearing for …

Part of Route 187 closed due to flooding
Part of Rt. 187 closed due to flooding

Flooding has closed a section of South Westfield Street (Route …

Memorial Day weekend travel forecast
Memorial Day weekend travel forecast

Memorial Day weekend tends to be a busy time on the roads …

Vigil for pedestrians killed
Vigil for pedestrians killed

Thursday night, the families of two pedestrians, killed more …

Advertisement

Greenfield covered bridge may re-open by summer

Updated: Thursday, 14 Mar 2013, 7:59 PM EDT
Published : Thursday, 14 Mar 2013, 5:20 PM EDT

GREENFIELD, Mass. (WWLP) - The covered bridge in Greenfield will likely open sometime this year.

The bridge, which spans the Green River, dropped about six feet and was knocked off its abutments when Tropical Storm Irene blew through Western Massachusetts in 2011.

Greenfield Engineering Superintendent Sara Campbell told 22News design plans to fix it are about 90% done. She says they hope to have the bridge open by the end of summer or early fall, because a lot of people rely on it.

“To have the ability to put cars across it again is critical to people out in that area, because they need to get down this way whether it's coming from Leyden down to the hospital, or basically just back and forth,” Campbell said.

Campbell says that the repairs will be funded mostly by FEMA.